Fire stopping handover inspection

Before the building is signed off, someone should check every seal against what it claims to be.

  • Every seal labelled and photographed
  • BM TRADA / FIRAS-certificated contractors
  • Written price before any work
Get a price

We reply with a written price.

We use these details to reply to you. See our privacy notice.

This is for main contractors, developers and clients near the end of a build or a fit-out. The fire stopping is in. The ceilings are about to close. Is it right?

Once the tiles go up and the boarding goes on, finding a missing seal means opening the building again.

A black corrugated conduit entering a wall just below a concrete soffit, with a lump of white foam round it
A black corrugated conduit entering a wall just below a concrete soffit, with a lump of white foam round it

What gets checked

Every accessible penetration and linear seal in the fire walls and floors, or an agreed sample.

For each seal: right product, right size, right depth, right face, matches the maker's tested detail for that wall or floor, tagged, and in the installer's record.

Also: services added after the fire stopping was done. On a busy site, the electrician often finishes after the fire stopper. Late cables are a common source of snags.

The snag list

Each failed seal gets a reference, a photo, the reason and the fix. Sorted by floor and area so the trades can work through it in order.

Example, made up:

S-114. Level 3, riser R2, east wall. Two data cables added through batt after sealing. Batt torn. Patch and mastic both faces, re-tag.

S-115. Level 3, corridor wall head gridline 4 to 6. Sealant 5mm deep, detail needs 15mm. Rake out and reseal.

Second visit

After the trades say the snags are closed, we check them again and close each one on the list with a photo. The final list goes in the handover file.

Who does what

We inspect and report. If you want the snags fixed by us, our BM TRADA / FIRAS-certificated contractors can do it, priced separately.

For higher-risk buildings, which are those at least 18 metres high or with at least seven storeys and at least two homes, the handover file matters even more, because the building has to be registered and its safety information kept.